2012 Construction Projects
Lulu East Watermain Upgrade
Project DescriptionThe existing watermains in this area are nearing the end of their life span. Completion of this project will improve water supply and reduce maintenance costs. The scope of work includes the replacement of the existing watermain, renewal of water service connections, and the replacement of existing fire hydrants.
Location
- 15000 block of Cambie Road
- 4000 block and 5000 block of No. 7 Road
General Considerations
- Typical hours of work will be from 7:00 am to 5:00 pm, Monday to Friday.
- Vehicle and pedestrian traffic may be limited at times.
- Residents and businesses will be notified in advance of any traffic disruption.
- If there is shrubbery fronting your property within the City corridor that you wish to retain in the immediate construction area, please remove it prior to project commencement. Trees cannot be relocated without a permit.
- Residents and businesses will be notified in advance of any scheduled water shutdowns.
- It may be necessary to excavate some driveway crossings. Crews will make every effort to notify you on the day prior to the work and again in the morning. At the end of each day, driveways that have been disturbed will be restored to a gravel condition.
Capital Funding
$ 1,635,868
Estimated Construction Period
Summer 2012
Project Manager
Mike Maxwell
Lulu North Watermain Upgrade – Voyageur Way
Project Description
The existing watermains in the area are nearing the end of their service life. The project on Voyageur Way is one of four projects in the Lulu North Waterworks Area. Completion of this project will improve water supply and will reduce maintenance costs. The scope of work includes the replacement of the existing watermain, renewal of water service connections, and the replacement of existing fire hydrants.
Locations
- Voyageur Way from Simpson Road to Olafsen Avenue
General Considerations
- Typical hours of work will be from 7:00 am to 5:00 pm, Monday to Friday.
- Vehicle and pedestrian traffic may be limited at times.
- Residents and businesses will be notified in advance of any traffic disruption.
- If there is shrubbery fronting your property within the City corridor that you wish to retain in the immediate construction area, please remove it prior to project commencement. Trees cannot be relocated without a permit.
- Businesses and residents will be notified in advance of any scheduled water shutdowns.
- It may be necessary to excavate some driveway crossings. Crews will make every effort to notify you on the day prior to the work and again in the morning. At the end of each day, driveways that have been disturbed will be restored to a gravel condition.
Capital Funding
$ 347,000
Estimated Construction Period
Summer/Fall 2012
Project Manager
Roger Keating
Lulu North Watermain Upgrade – Woodhead Road
Project Description
The existing watermains in this area are nearing the end of their service life. The Woodhead Road project is one of four projects in the Lulu North Waterworks Area. Completion of this project will improve water supply and will reduce maintenance costs. The scope of work includes the replacement of the existing watermain, renewal of water service connections, and the replacement of existing fire hydrants.
Locations
- Woodhead Road from No. 5 Road to Montego Street
General Considerations
- Typical hours of work will be from 7:00 am to 5:00 pm, Monday to Friday.
- Vehicle and pedestrian traffic may be limited at times.
- Residents and businesses will be notified in advance of any traffic disruption.
- If there is shrubbery fronting your property within the City corridor that you wish to retain in the immediate construction area, please remove it prior to project commencement. Trees cannot be relocated without a permit.
- Businesses and residents will be notified in advance of any scheduled water shutdowns.
- It may be necessary to excavate some driveway crossings. Crews will make every effort to notify you on the day prior to the work and again in the morning. At the end of each day, driveways that have been disturbed will be restored to a gravel condition.
Capital Funding
$ 408,000
Estimated Construction Period
Summer 2012
Project Manager
Mike Maxwell
Lulu North Watermain Upgrade – Alexandra Road
Project Description
The existing watermains in this area are nearing the end of their life span. The Alexandra Road project is one of four projects in the Lulu North Waterworks Area. Completion of this project will improve water supply and will reduce maintenance costs. The scope of work includes the replacement of the existing watermain, renewal of water service connections, and the replacement of existing fire hydrants.
Location
- Alexandra Road from No. 3 Road to Garden City Road
General Considerations
- Typical hours of work will be from 7:00 am to 5:00 pm, Monday to Friday.
- Vehicle and pedestrian traffic may be limited at times.
- Residents and businesses will be notified in advance of any traffic disruption.
- If there is shrubbery fronting your property within the City corridor that you wish to retain in the immediate construction area, please remove it prior to project commencement. Trees cannot be relocated without a permit.
- Businesses and residents will be notified in advance of any scheduled water shutdowns.
- It may be necessary to excavate some driveway crossings. Crews will make every effort to notify you on the day prior to the work and again in the morning. At the end of each day, driveways that have been disturbed will be restored to a gravel condition.
Capital Funding
$ 1,235,000
Estimated Construction Period
Summer/Fall 2012
Project Manager
Roger Keating
Lulu North Watermain Upgrade – Ackroyd Road
Project Description
The existing watermains in this area are nearing the end of their life span. The Ackroyd Road project is one of four projects in the Lulu North Waterworks Area. Completion of this project will improve water supply and will reduce maintenance costs. The scope of work includes the replacement of the existing watermain, renewal of water service connections, and the replacement of existing fire hydrants.
Location
- 8000 Block of Ackroyd Road
General Considerations
- Typical hours of work will be from 7:00 am to 5:00 pm, Monday to Friday.
- Vehicle and pedestrian traffic may be limited at times.
- Residents and businesses will be notified in advance of any traffic disruption.
- If there is shrubbery fronting your property within the City corridor that you wish to retain in the immediate construction area, please remove it prior to project commencement. Trees cannot be relocated without a permit.
- Businesses and residents will be notified in advance of any scheduled water shutdowns.
- It may be necessary to excavate some driveway crossings. Crews will make every effort to notify you on the day prior to the work and again in the morning. At the end of each day, driveways that have been disturbed will be restored to a gravel condition.
Capital Funding
$ 1,022,000
Estimated Construction Period
Summer/Fall 2012
Project Manager
Roger Keating
Lulu West Watermain Upgrade
Project Description
The existing watermains in this area are nearing the end of their life span. Completion of this project will improve water supply and will reduce maintenance costs. The scope of work includes the replacement of the existing watermain, renewal of water service connections, and the replacement of existing fire hydrants.
Location
8000 block and 9000 block of Williams Road
General Considerations
- Typical hours of work will be from 7:00 am to 5:00 pm, Monday to Friday.
- Vehicle and pedestrian traffic may be limited at times.
- Residents and businesses will be notified in advance of any traffic disruption.
- If there is shrubbery fronting your property within the City corridor that you wish to retain in the immediate construction area, please remove it prior to project commencement. Trees cannot be relocated without a permit.
- Residents and businesses will be notified in advance of any scheduled water shutdowns.
- It may be necessary to excavate some driveway crossings. Crews will make every effort to notify you on the day prior to the work and again in the morning. At the end of each day, driveways that have been disturbed will be restored to a gravel condition.
Capital Funding
$ 1,623,248
Estimated Construction Period
Spring/Summer 2012
Project Manager
Roger Keating
Sea Island Watermain Upgrade
Project Description
The existing watermains in this area are nearing the end of their life span. Completion of this project will improve water supply and will reduce maintenance costs. The scope of work includes the replacement of the existing watermain, renewal of water service connections, and the replacement of existing fire hydrants.
Locations
- Douglas Crescent
- Boeing Avenue at Wellington Crescent to 50m north of Wellington Crescent
- Wellington Crescent from Catalina Crescent to Lancaster Crescent
General Considerations
- Typical hours of work will be from 7:00 am to 5:00 pm, Monday to Friday.
- Vehicle and pedestrian traffic may be limited at times.
- Residents and businesses will be notified in advance of any traffic disruption.
- If there is shrubbery fronting your property within the City corridor that you wish to retain in the immediate construction area, please remove it prior to project commencement. Trees cannot be relocated without a permit.
- Residents and businesses will be notified in advance of any scheduled water shutdowns.
- It may be necessary to excavate some driveway crossings. Crews will make every effort to notify you on the day prior to the work and again in the morning. At the end of each day, driveways that have been disturbed will be restored to a gravel condition.
Capital Funding
$ 670,832
Estimated Construction Period
Summer/Fall 2012
Project Manager
Mike Maxwell
Gravity Sanitary Sewer Upgrade on Leslie Road and Brown Road
Project Description
The existing gravity sanitary sewer is nearing the end of its service life. Completion of this project is required to minimize the risk of pipe failure and upgrade the pipes to meet future demand. The scope of work includes the replacement and upsizing of the existing sanitary sewer main, and reconnection of existing sanitary sewer services.
Location
- 8000 Block of Leslie Road
- Brown Road from Leslie Road to Odlin Crescent
General Considerations
- Typical hours of work will be from 7:00am to 5:00pm, Monday to Friday.
- Vehicle and pedestrian traffic may be limited at times.
- Residents and businesses will be notified in advance of any traffic disruption.
- If there is shrubbery fronting your property within the City corridor that you wish to retain in the immediate construction area, please remove it prior to project commencement. Trees cannot be relocated without a permit.
- Residents and businesses will be notified in advance of any scheduled disruption to sanitary sewer service. Minimal disruption to sanitary service is anticipated.
- Night work may be required to complete final connections.
- It may be necessary to excavate some driveway crossings. Crews will make every effort to notify you on the day prior to the work and again in the morning. At the end of each day, driveways that have been disturbed will be restored to a gravel condition.
Capital Funding
$ 1,509,000
Estimated Construction Period
Fall 2012
Project Manager
Roger Keating
Blundell Road Sanitary Sewer Forcemain Replacement
Project Description
The existing fibreglass sanitary sewer forcemain is nearing the end of its service life. This project is required to reduce the risk of sewer overflows due to forcemain breaks and to reduce maintenance costs. The scope of work includes the replacement of the existing sanitary sewer forcemain and connection to the existing sanitary system. Completion of this project will ensure critical service is maintained for the 17 pump stations in the Terra Nova sanitary sewer system.
Location
Blundell Road from Frobisher Drive to Railway Avenue
General Considerations
- Typical hours of work will be from 7:00am to 5:00pm, Monday to Friday.
- Vehicle and pedestrian traffic may be limited at times.
- Residents and businesses will be notified in advance of any traffic disruption.
- Minimal disruption to sanitary services is anticipated. Residents and businesses will be notified in advance of any scheduled disruption to sanitary sewer service.
- Night work may be required to complete final connections
- It may be necessary to excavate some driveway crossings. Crews will make every effort to notify you on the day prior to the work and again in the morning. At the end of each day, driveways that have been disturbed will be restored to a gravel condition.
Capital Funding
$ 1,427,000
Estimated Construction Period
Fall 2012
Project Manager
Roger Keating
No. 1 Road North Drainage Pump Station Upgrade
Project Description
The existing No. 1 Road North drainage pump station is nearing the end of its service life and is not able to meet the demands of future development. Completion of this station will replace the existing structure, modernize the equipment and increase the pumping capacity from 1.98 cubic meters per second to 4.5 cubic meters per second to meet future predicted flows.
Location
No. 1 Road at River Road
General Considerations
- Typical hours of work will be from 7:00 am to 5:00 pm, Monday to Friday.
- Vehicle and pedestrian traffic along River Road and No. 1 Road may be limited at times.
- Pedestrian and trail traffic will be detoured around the construction site.
- Residents and businesses will be notified in advance of any traffic disruption.
- Diking, fisheries and other government agencies will be consulted through design and construction.
Capital Funding
$ 3,450,000
Estimated Construction Period
Summer/Fall 2012
Project Manager
Mile Racic
Williams Road West Drainage Pump Station Upgrade
Project Description
The existing Williams Road West drainage pump station is nearing the end of its service life and is not able to meet the demands of future development. Completion of this station will replace the existing structure, modernize the equipment and increase the pumping capacity from 0.73 cubic meters per second to 1.5 cubic meters per second.
Location
West end of Williams Road
General Considerations
- Typical hours of work will be from 7:00 am to 5:00 pm, Monday to Friday.
- Vehicle and pedestrian traffic may be limited at times.
- Residents and businesses will be notified in advance of any traffic disruption.
- Pedestrian and trail traffic will be detoured around the construction site.
- Diking, fisheries and other government agencies will be consulted through design and construction.
Capital Funding
$1,950,000
Estimated Construction Period
Summer/Fall 2012
Project Manager
Mile Racic
No. 6 Road Drainage and Irrigation Upgrade
Project Description
The existing drainage ditch along the east side of No. 6 Road between Bridgeport Road and Cambie Road will be re-profiled to improve irrigation and drainage.
Location
3000 block of No. 6 Road
General Considerations
- Typical hours of work will be from 7:00 am to 5:00 pm, Monday to Friday.
- Vehicle and pedestrian traffic may be limited at times.
- Residents and businesses will be notified in advance of any traffic disruption.
- Fisheries, environmental and other government agencies will be consulted through design and construction.
- Residents and businesses will be notified in advance of any scheduled water shutdowns.
- Coordination with the farming community is on-going
Capital Funding
$ 371,000
Estimated Construction Period
Summer 2012
Project Manager
Anthony Fu, P.Eng.
Seaton Road Laneway Drainage Upgrade
Project Description
The existing laneway south of Seaton Road has a history of drainage issues during significant storm events. The objective of this project is to address these drainage issues by constructing a new storm water collection system and repaving the laneway.
Location
Laneway south of Seaton Road between Shell Road and 11720 Seaton Road
General Considerations
- It will be necessary to close the laneway for construction. Notice of construction and the locations for temporary parking and garbage/recycling pickup will be provided in advance.
- Typical hours of work will be from 7:00 am to 5:00 pm, Monday to Friday.
- Vehicle and pedestrian traffic may be limited at times.
- Residents will be notified in advance of any traffic disruption.
- If there is shrubbery fronting your property within the City corridor that you wish to retain in the immediate construction area, please remove it prior to project commencement. Trees cannot be relocated without a permit.
- Residents will be notified in advance of any scheduled disruptions to sanitary sewer service. Minimal disruptions to service are anticipated.
Capital Funding
$ 631,572
Estimated Construction Period
Summer/Fall 2012
Project Manager
Anthony Fu, P.Eng.
Williams Road Laneway Drainage Upgrade
Project Description
The existing laneway south of Williams Road between No. 4 Road and Aragon Road has a history of flooding during significant storm events. The objective of this project is to address these drainage issues by constructing a new storm water collection system and repaving the laneway.
The laneway from Aragon Road to Aquila Road is being constructed by adjacent development; the remaining portion of the laneway, from Aquila Road to Dennis Place, will be constructed as a Capital Project.
Location
Laneway south of 10000 block Williams Road between No. 4 Road and Aragon Road
General Considerations
- It will be necessary to close the laneway for construction. Notice of construction and the locations for temporary parking and garbage/recycling pickup will be provided in advance.
- Typical hours of work will be from 7:00 am to 5:00 pm, Monday to Friday.
- Vehicle and pedestrian traffic may be limited at times.
- Residents will be notified in advance of any traffic disruption.
- If there is shrubbery fronting your property within the City corridor that you wish to retain in the immediate construction area, please remove it prior to project commencement. Trees cannot be relocated without a permit.
- Residents will be notified in advance of any scheduled disruptions to sanitary sewer service. Minimal disruptions to service are anticipated.
Capital Funding
$ 429,378
Estimated Construction Period
Summer/Fall 2012
Project Manager
Anthony Fu, P.Eng.
No. 6 Road Widening
Project Description
Northbound No. 6 Road is currently 1 lane wide between Wireless Way and Commerce Parkway. To better serve goods movement with an improved connection between Westminster Highway and Highway 91, this section of No. 6 Road will be widened to 2 lanes. Shared walkway / bike paths will also be constructed from Westminster Highway to Commerce Parkway, along with drainage improvements to accommodate the widened roadway.
Location
No. 6 Road from Wireless Way to Commerce Parkway
General Considerations
- Typical hours of work will be from 7:00 am to 5:00 pm, Monday to Friday.
- Vehicle and pedestrian traffic may be limited at times.
- Businesses and residents will be notified in advance of any traffic disruption.
- Fisheries and other government agencies will be consulted through design and construction.
Capital Funding
2012: $ 566,667 / Total Funding (2011-2013): $1,700,000
Estimated Construction Period
2012-2013
Project Manager
Mile Racic
Westminster Highway and Nelson Road Widening
Project Description
Westminster Highway was originally 2 lanes wide between No. 6 Road and Highway 91 at the Hamilton Interchange. Nelson Road south of Westminster Highway is currently 2 lanes wide. As the amount of industrial activity has increased in the Port Metro Vancouver lands at the south ends of No 8 Road and Nelson Road, there has been a corresponding increase in the amount of heavy vehicle traffic on Westminster Highway. To address this traffic, the following projects have been identified by the City of Richmond, Province of British Columbia, and Port Metro Vancouver:
- Widening Westminster Highway from McMillan Way to Highway 91 at the Hamilton Interchange from 2 lanes to 4 lanes including cycling facilities (completed in 2006)
- A new interchange at Highway 91 and Nelson Road (completed in 2011)
- Widening Westminster Highway from Nelson Road to McMillan Way from 2 lanes to 4 lanes including off-road pedestrian and cycling facilities (this project)
- Widening Nelson Road from Blundell Road to Westminster Highway from 2 lanes to 4 lanes including off-road pedestrian and cycling facilities (this project)
Location
Westminster Highway – Nelson Road to McMillan Way
Nelson Road – Blundell Road to Westminster Highway
General Considerations
- Typical hours of work will be from 7:00 am to 5:00 pm, Monday to Friday.
- Vehicle and pedestrian traffic may be limited at times.
- Businesses and residents will be notified in advance of any traffic disruption.
- Fisheries and other government agencies will be consulted through design and construction.
Capital Funding
2012: $3,834,000 / Total Funding (2011-2012): $11,492,000
Estimated Construction Period
2012 to Winter 2013
Project Manager
Milton Chan, P.Eng.
Annual Asphalt Re-Paving Program
Click here to be directed to the 2012 Capital Paving Program website.
Automation of No. 3 Road South and Horseshoe Slough Pump Station Irrigation Valves
Project Description
Richmond’s watercourses provide water for farm irrigation. Automation of the irrigation valves at the No. 3 Road South and Horseshoe Slough pump stations will provide more consistent watercourse elevations in the respective service areas south of Steveston Highway. The project will also reduce potable water consumption by farmers in cooperation with Metro Vancouver’s current Liquid Waste Management Plan. Automating the valves will also reduce drainage pump station power consumption and will reduce associated wear and tear on pumping equipment. The project may also reduce operator field visits for valve control.
Location
No. 3 Road at Dyke Road
Dyke Road between Shell Road and No. 5 Road
General Considerations
- Typical hours of work will be from 7:00 am to 5:00 pm, Monday to Friday.
- Vehicle and pedestrian traffic may be limited at times. Businesses and residents will be notified in advance of any traffic disruption.
- Businesses and residents will be notified in advance of any scheduled water shutdowns.
- Diking, other government agencies and farmers will be consulted through design and construction.
Capital Funding
$ 100,000
Estimated Construction Period
Summer/Fall 2012
Project Manager
Derek Hunter
Gilbert South Pump Station Generator
Project Description
Repairing flood damage can be expensive. Adding a back-up generator at the Gilbert Road South drainage pump station will help prevent flooding during a local BC Hydro power failure and could help reduce emergency operations and maintenance costs. The project, which is part of a larger strategy to add back-up generators to pump stations around Richmond, will include the construction of a concrete pad and installation of a generator and transfer switch.
Location
Gilbert Road at Dyke Road
General Considerations
- Typical hours of work will be from 7:00 am to 5:00 pm, Monday to Friday.
- Vehicle and pedestrian traffic may be limited at times. Businesses and residents will be notified in advance of any traffic disruption.
- Businesses and residents will be notified in advance of any scheduled water shutdowns.
- Diking, fisheries and other governmental agencies will be consulted through design and construction.
Capital Funding
$ 100,000
Estimated Construction Period
Summer/Fall 2012
Project Manager
Derek Hunter
Long Shaft Pump Replacement Program
Three of the City's drainage pump stations have aging long shaft pumps that are in need of replacement. The pumps are outdated and replacement parts are no longer available. New KSB and Flygt pumps will be installed with Variable Frequency Drives at several pump stations resulting in energy and cost savings.
- Compared to submersible pumps, long shaft pumps are costly to maintain and challenging to service, especially in the event of blockage or failure.
Submersible pumps are 30-40% more energy efficient than the long shaft pumps. - KSB/Flygt pumps are approximately the same dimensions as the long shaft pumps eliminating the need for costly retrofits or renovations to the pump stations.
- Variable Frequency Drives (VFD) provide energy efficiency by varying the speed of the pump in response to the water level rather than running the pump at a set speed which may be higher than required while accomplishing the same result.
- VFD's extend the service life of the pump and electrical system by reducing hydraulic and mechanical stresses in the pump and electrical components and thermal stresses in the motor control system associated with cycling the pump on and off.
- Extend service life of outfall infrastructure by maintaining a more constant water flow compared to a surges of water and possible water hammer generated by pump cycles.
This is the second year of a four year program.
Location
Woodward Slough
Horseshoe Slough
No. 7 Road South
General Considerations
- Typical hours of work will be from 7:00 am to 5:00 pm, Monday to Friday.
- Vehicle and pedestrian traffic may be limited at times.
- Fisheries, fisheries and other government agencies will be consulted through design and construction.
Capital Funding
$ 450,000
Estimated Construction Period
On-going
Project Manager
Derek Hunter
McCallan Road North Pump Station MCC Upgrade
Project Description
As part of a larger strategy to minimize the potential for flood related damage, the City is installing back-up generators at pump stations around Richmond in the event of local power failures. In preparation for adding a back-up generator at the McCallan Road drainage pump in the future, the station’s motor control centre is being modernized to provide reliable flood protection service.
Location
McCallan Road and River Road
General Considerations
- Typical hours of work will be from 7:00 am to 5:00 pm, Monday to Friday.
- Vehicle and pedestrian traffic may be limited at times. Businesses and residents will be notified in advance of any traffic disruption.
- Businesses and residents will be notified in advance of any scheduled water shutdowns.
- Diking, fisheries and other governmental agencies will be consulted through design and construction.
Capital Funding
$ 175,000
Estimated Construction Period
Summer/Fall 2012
Project Manager
Derek Hunter
No. 6 Road North Pump Station Generator
Project Description
Repairing flood damage can be expensive. Adding a back-up generator at the Gilbert Road South drainage pump station helps prevent flooding during a local BC Hydro power failure and can help reduce emergency operations and maintenance costs. The project, which is part of a larger strategy to add back-up generators to pump stations around Richmond, will include the construction of a concrete pad and installation of a generator and transfer switch.
Location
No. 6 Road and River Road
General Considerations
- Typical hours of work will be from 7:00 am to 5:00 pm, Monday to Friday.
- Vehicle and pedestrian traffic may be limited at times. Businesses and residents will be notified in advance of any traffic disruption.
- Businesses and residents will be notified in advance of any scheduled water shutdowns.
- Diking, fisheries and other governmental agencies will be consulted through design and construction.
Capital Funding
$ 120,000
Estimated Construction Period
Summer/Fall 2012
Project Manager
Derek Hunter
Pump Station Level Control Upgrade
Project Description
The City relies on 39 drainage pump stations as part of its flood protection system. Having modern and reliable drainage infrastructure ensures that the system is able to respond to high water level situations. Completion of this project will update the float level controls to sonar level controls at several pump stations to increase pump station reliability to ensure continued flood protection.
Locations
No. 3 Road South
Nelson Road South
Queen Road North
No. 6 Road North
Dog Kennels
Green Slough
Miller Road
General Considerations
- Typical hours of work will be from 7:00 am to 5:00 pm, Monday to Friday.
- Vehicle and pedestrian traffic may be limited at times.
- Businesses and residents will be notified in advance of any traffic disruption.
- Businesses and residents will be notified in advance of any scheduled water shutdowns.
- Diking, environmental, and other government agencies will be consulted through design and construction.
Capital Funding
$ 140,000
Estimated Construction Period
Summer/Fall 2012
Project Manager
Derek Hunter
Canal Stabilization
Project Description
With continued development the drainage system is conveying higher volumes of water and experiencing a higher rate of degradation of the canal banks. This results in road shoulder and ditch bank failures as well as potential reduction in the City’s ability to convey runoff and irrigation water. To prevent damage to public and private property and ensure the effectiveness of the canal, it is important to undertake canal stabilization projects. Solutions include partial re-profiling of the canal plus construction of a retaining wall or similar stabilisation structures. This project will stabilise the No. 3 Road Canal and No. 8 Road Canal walls to improve drainage, mitigate damage to the roadway, prevent damage to City utilities running parallel to the canals and preserve valuable riparian habitat.
Location
No. 3 Road (various locations south of Steveston Highway)
No. 8 Road (2000 block)
General Considerations
- Typical hours of work will be from 7:00 am to 5:00 pm, Monday to Friday.
- Vehicle and pedestrian traffic may be limited at times. Businesses and residents will be notified in advance of any traffic disruption.
- Businesses will be notified in advance of any scheduled water shutdowns.
- Department of Fisheries and Oceans, other governmental agencies and farmers will be consulted through design and construction.
Capital Funding
$300,000
Estimated Construction Period
Fall 2012
Project Manager
Michael Schwanke, EIT
Minoru Pump Station Upgrade
Project Description
The existing Minoru sanitary sewer pump station does not have adequate capacity to serve the area’s growing population. With the catchment experiencing rapid high density re-development, the pump station will be designed to service 2041 OCP population projections. The project will include construction of a new pump station, inlet gravity sewer and forcemain.
Location
Lane North of 5600 Cedarbridge Way
General Considerations
- Typical hours of work will be from 7:00 am to 5:00 pm, Monday to Friday.
- Vehicle and pedestrian traffic may be limited at times. Businesses and residents will be notified in advance of any traffic disruption.
- Businesses and residents will be notified in advance of any scheduled water shutdowns or disruption to sanitary sewer service.
Capital Funding
$ 2,874,000
Estimated Construction Period
Fall 2012/Spring 2013
Project Manager
Roger Keating
Pump Station and Forcemain Assessment and Upgrade
Project Description
This project includes the assessment of forcemains and pump stations and the implementation of improvements particularly those oriented towards grease mitigation, emergency by-pass, or based on the assessments. Completion of this project will extend of pump station and forcemain service life, reduce service interruptions, reduce emergency expenditures and potential health hazards due to forcemain blockages, reduce property damage and environmental damage associated with sanitary sewer overflows, and reduce forcemain breaks and blockages.
Location
City Wide
General Considerations
- Typical hours of work will be from 7:00 am to 5:00 pm, Monday to Friday.
- Vehicle and pedestrian traffic may be limited at times.
- Residents and businesses will be notified in advance of construction projects resulting from assessments.
Capital Funding
$ 750,000
Estimated Construction Period
TBD
Project Manager
Elena Paller, P.Eng.
Sanitary Sewer Replacement at 6331/6351 Cooney Road (City Centre Area)
Project Description
Located in a Right-of-Way at the back of the properties and in close proximity to buildings, the sanitary main was identified as having a high risk of failure. Accessing the main to perform an emergency repair would be difficult. Completion of this project will relocate the main to the roadway and will adjust the connections providing residents and businesses with high levels of service in the long term and will reduce costly unplanned maintenance.
Location
6331/6351 Cooney Road
General Considerations
- Typical hours of work will be from 7:00 am to 5:00 pm, Monday to Friday.
- Vehicle and pedestrian traffic may be limited at times. Businesses and residents will be notified in advance of any traffic disruption.
- Businesses and residents will be notified in advance of any scheduled water shutdowns or disruptions to sanitary sewer service.
Capital Funding
$ 296,000
Estimated Construction Period
Fall 2012
Project Manager
Roger Keating